24,000+ questions & coding problemsSoftware & IT16,274 questionsGovernment jobs26 examsAptitudenew questions every timeAI practice interviewwith feedback65 topics to practiseMechanical1,149 questionsGATE ME9 papersEngineering Mathematics381 questions2-minute checkfreeDSA Problems1,422Civil1,005 questionsGATE CE9 papersCS Fundamentals1,209 questionsYour scores6 skillsSystem Design25Electrical / EEE1,047 questionsGATE EE9 papersRun your codeC++ · Java · PythonLow-Level Design144Electronics & Comm.975 questionsGATE EC9 papersAI help on every questionFull-Stack6,282Chemical1,005 questionsGATE CH9 papersAI whiteboardsystem designWork abroadEurope · remote · transfersESE ME1 paperGATE practice papers2019–2026ESE CE1 paperDate alertsbefore the last dateESE EE1 paperBehavioural courseHR round practiceESE ET1 paperResume optimizerSSC JE ME1 paperApplication trackerSSC JE CE1 paperCompany-wise prepSSC JE EE1 paperRole roadmapsRRB JE1 subjectPriced in ₹UPI · cardsISRO SC1 paperGATE CS9 papersIBPS SO IT1 paperUGC NET CS1 paperSSC CGL26 papersIBPS PO26 papersRRB NTPC26 papersSSC CHSL26 papersIBPS Clerk26 papersSBI Clerk26 papersRRB Group D26 papersSSC CPO26 papersSSC GD26 papers

Quantity Surveying & Billing interview questions

27 real Quantity Surveying & Billing questions from the Site & Project Mgmt bank, as asked in Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd — free to start.

1. What is Measurement book?

Junior
  1. A.page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  2. B.security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  3. C.comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates
  4. D.CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period
Reveal the answer + AI explanation — free account

2. Which term means: "page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill"?

Junior
  1. A.Measurement book
  2. B.Price escalation clause
  3. C.Wastage norms
  4. D.Material reconciliation
Reveal the answer + AI explanation — free account

3. Which statement is correct?

Junior
  1. A.Measurement book — payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  2. B.Measurement book — rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
  3. C.Measurement book — security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  4. D.Measurement book — page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
Reveal the answer + AI explanation — free account

4. What is Running account bill?

Junior
  1. A.security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  2. B.page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  3. C.interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
  4. D.about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
Reveal the answer + AI explanation — free account

5. Which term means: "interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals"?

Junior
  1. A.Running account bill
  2. B.Extra item rate
  3. C.Bill deductions
  4. D.Measurement book
Reveal the answer + AI explanation — free account

6. Which statement is correct?

Junior
  1. A.Running account bill — comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates
  2. B.Running account bill — payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  3. C.Running account bill — interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
  4. D.Running account bill — rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
Reveal the answer + AI explanation — free account

7. What is Bill deductions?

Junior
  1. A.comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates
  2. B.security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  3. C.about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  4. D.rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
Reveal the answer + AI explanation — free account

8. Which term means: "security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued"?

Junior
  1. A.Wastage norms
  2. B.Price escalation clause
  3. C.Bill deductions
  4. D.Measurement book
Reveal the answer + AI explanation — free account

9. Which statement is correct?

Junior
  1. A.Bill deductions — payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  2. B.Bill deductions — security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  3. C.Bill deductions — about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  4. D.Bill deductions — interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
Reveal the answer + AI explanation — free account

10. What is Secured advance?

Mid
  1. A.CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period
  2. B.payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  3. C.about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  4. D.allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
Reveal the answer + AI explanation — free account

11. Which term means: "payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed"?

Mid
  1. A.Wastage norms
  2. B.Bill deductions
  3. C.Secured advance
  4. D.Measurement book
Reveal the answer + AI explanation — free account

12. Which statement is correct?

Mid
  1. A.Secured advance — payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  2. B.Secured advance — allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
  3. C.Secured advance — page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  4. D.Secured advance — rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
Reveal the answer + AI explanation — free account

13. What is Material reconciliation?

Mid
  1. A.comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates
  2. B.security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  3. C.allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
  4. D.payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
Reveal the answer + AI explanation — free account

14. Which term means: "comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates"?

Mid
  1. A.Price escalation clause
  2. B.Secured advance
  3. C.Wastage norms
  4. D.Material reconciliation
Reveal the answer + AI explanation — free account

15. Which statement is correct?

Mid
  1. A.Material reconciliation — allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
  2. B.Material reconciliation — page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  3. C.Material reconciliation — about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  4. D.Material reconciliation — comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates
Reveal the answer + AI explanation — free account

16. What is Cement consumption norms?

Mid
  1. A.interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
  2. B.about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  3. C.rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
  4. D.security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
Reveal the answer + AI explanation — free account

17. Which term means: "about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design"?

Mid
  1. A.Extra item rate
  2. B.Cement consumption norms
  3. C.Secured advance
  4. D.Material reconciliation
Reveal the answer + AI explanation — free account

18. Which statement is correct?

Mid
  1. A.Cement consumption norms — payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  2. B.Cement consumption norms — about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  3. C.Cement consumption norms — page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  4. D.Cement consumption norms — interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
Reveal the answer + AI explanation — free account

19. What is Price escalation clause?

Senior
  1. A.security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  2. B.CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period
  3. C.page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  4. D.payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
Reveal the answer + AI explanation — free account

20. Which term means: "CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period"?

Senior
  1. A.Bill deductions
  2. B.Secured advance
  3. C.Measurement book
  4. D.Price escalation clause
Reveal the answer + AI explanation — free account

21. Which statement is correct?

Senior
  1. A.Price escalation clause — comparison of theoretical cement and steel consumption from measured work with actual issue, excess beyond the permitted variation recovered at penal rates
  2. B.Price escalation clause — security deposit, advance recovery, income tax TDS at 2 percent, GST TDS on government works, labour cess at 1 percent and cost of material issued
  3. C.Price escalation clause — allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
  4. D.Price escalation clause — CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period
Reveal the answer + AI explanation — free account

22. What is Extra item rate?

Mid
  1. A.interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
  2. B.rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
  3. C.allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
  4. D.page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
Reveal the answer + AI explanation — free account

23. Which term means: "rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead"?

Mid
  1. A.Cement consumption norms
  2. B.Running account bill
  3. C.Price escalation clause
  4. D.Extra item rate
Reveal the answer + AI explanation — free account

24. Which statement is correct?

Mid
  1. A.Extra item rate — CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period
  2. B.Extra item rate — about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  3. C.Extra item rate — allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
  4. D.Extra item rate — rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
Reveal the answer + AI explanation — free account

25. What is Wastage norms?

Senior
  1. A.rate for work outside the BOQ derived from schedule rates and cost index, or from market rate analysis plus contractor's profit and overhead
  2. B.CPWD clause 10CC adjusts payments for labour, material and fuel using published indices on long-duration contracts, applied to work done in each period
  3. C.interim bill for cumulative work done to date, less all previous payments and less deductions, submitted at agreed intervals
  4. D.allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
Reveal the answer + AI explanation — free account

26. Which term means: "allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation"?

Senior
  1. A.Material reconciliation
  2. B.Price escalation clause
  3. C.Wastage norms
  4. D.Bill deductions
Reveal the answer + AI explanation — free account

27. Which statement is correct?

Senior
  1. A.Wastage norms — page-numbered official record of work measured on site, signed by contractor and engineer without erasures, the sole basis for every bill
  2. B.Wastage norms — about 6.4 bags per cubic metre for 1:2:4 and 7.9 bags for 1:1.5:3 nominal mixes, with design mixes governed by the approved mix design
  3. C.Wastage norms — payment of up to 75 percent of the value of non-perishable materials brought to site against an indemnity bond, recovered as the material is consumed
  4. D.Wastage norms — allowances of about 3 to 5 percent on steel, 2 to 3 percent on cement, 5 percent on bricks and 5 to 7 percent on tiles built into rate analysis and reconciliation
Reveal the answer + AI explanation — free account

Free to start

Answers, AI explanations, and a free readiness check

Sign up free to check your answers with explanations, ask the AI tutor anything on any question, and take the free 2-minute readiness check for a scored result. The full AI mock interview, scored like a real panel, unlocks with Pro.

Practice Quantity Surveying & Billing free