24,000+ questions & coding problemsSoftware & IT16,274 questionsGovernment jobs26 examsAptitudenew questions every timeAI practice interviewwith feedback65 topics to practiseMechanical1,149 questionsGATE ME9 papersEngineering Mathematics381 questions2-minute checkfreeDSA Problems1,422Civil1,005 questionsGATE CE9 papersCS Fundamentals1,209 questionsYour scores6 skillsSystem Design25Electrical / EEE1,047 questionsGATE EE9 papersRun your codeC++ · Java · PythonLow-Level Design144Electronics & Comm.975 questionsGATE EC9 papersAI help on every questionFull-Stack6,282Chemical1,005 questionsGATE CH9 papersAI whiteboardsystem designWork abroadEurope · remote · transfersESE ME1 paperGATE practice papers2019–2026ESE CE1 paperDate alertsbefore the last dateESE EE1 paperBehavioural courseHR round practiceESE ET1 paperResume optimizerSSC JE ME1 paperApplication trackerSSC JE CE1 paperCompany-wise prepSSC JE EE1 paperRole roadmapsRRB JE1 subjectPriced in ₹UPI · cardsISRO SC1 paperGATE CS9 papersIBPS SO IT1 paperUGC NET CS1 paperSSC CGL26 papersIBPS PO26 papersRRB NTPC26 papersSSC CHSL26 papersIBPS Clerk26 papersSBI Clerk26 papersRRB Group D26 papersSSC CPO26 papersSSC GD26 papers

QA/QC & Testing interview questions

30 real QA/QC & Testing questions from the Site & Project Mgmt bank, as asked in Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd — free to start.

1. What is Slump test?

Junior
  1. A.IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  2. B.surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  3. C.IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³
  4. D.concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent
Reveal the answer + AI explanation — free account

2. Which term means: "IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected"?

Junior
  1. A.Rebound hammer test
  2. B.Slump test
  3. C.Inspection and test plan
  4. D.Field density test
Reveal the answer + AI explanation — free account

3. Which statement is correct?

Junior
  1. A.Slump test — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  2. B.Slump test — sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade
  3. C.Slump test — IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  4. D.Slump test — IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength
Reveal the answer + AI explanation — free account

4. What is Cube compressive test?

Junior
  1. A.sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade
  2. B.IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength
  3. C.IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  4. D.IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³
Reveal the answer + AI explanation — free account

5. Which term means: "IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength"?

Junior
  1. A.Cube compressive test
  2. B.Field density test
  3. C.Sampling frequency
  4. D.Aggregate mechanical tests
Reveal the answer + AI explanation — free account

6. Which statement is correct?

Junior
  1. A.Cube compressive test — IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength
  2. B.Cube compressive test — IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  3. C.Cube compressive test — activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
  4. D.Cube compressive test — surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
Reveal the answer + AI explanation — free account

7. What is Sampling frequency?

Junior
  1. A.IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³
  2. B.IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads
  3. C.surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  4. D.IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
Reveal the answer + AI explanation — free account

8. Which term means: "IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³"?

Junior
  1. A.Cube compressive test
  2. B.Field density test
  3. C.Sampling frequency
  4. D.Slump test
Reveal the answer + AI explanation — free account

9. Which statement is correct?

Junior
  1. A.Sampling frequency — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  2. B.Sampling frequency — surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  3. C.Sampling frequency — activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
  4. D.Sampling frequency — IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³
Reveal the answer + AI explanation — free account

10. What is Rebound hammer test?

Mid
  1. A.formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  2. B.activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
  3. C.IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  4. D.surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
Reveal the answer + AI explanation — free account

11. Which term means: "surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance"?

Mid
  1. A.Field density test
  2. B.Rebound hammer test
  3. C.Non-conformance report
  4. D.Slump test
Reveal the answer + AI explanation — free account

12. Which statement is correct?

Mid
  1. A.Rebound hammer test — surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  2. B.Rebound hammer test — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  3. C.Rebound hammer test — IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  4. D.Rebound hammer test — IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
Reveal the answer + AI explanation — free account

13. What is Ultrasonic pulse velocity?

Mid
  1. A.sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade
  2. B.IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  3. C.IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  4. D.activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
Reveal the answer + AI explanation — free account

14. Which term means: "IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks"?

Mid
  1. A.Sampling frequency
  2. B.Non-conformance report
  3. C.Ultrasonic pulse velocity
  4. D.Slump test
Reveal the answer + AI explanation — free account

15. Which statement is correct?

Mid
  1. A.Ultrasonic pulse velocity — IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  2. B.Ultrasonic pulse velocity — IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  3. C.Ultrasonic pulse velocity — surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  4. D.Ultrasonic pulse velocity — IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads
Reveal the answer + AI explanation — free account

16. What is Core test acceptance?

Senior
  1. A.IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  2. B.activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
  3. C.concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent
  4. D.IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
Reveal the answer + AI explanation — free account

17. Which term means: "concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent"?

Senior
  1. A.Aggregate mechanical tests
  2. B.Core test acceptance
  3. C.Sampling frequency
  4. D.Field density test
Reveal the answer + AI explanation — free account

18. Which statement is correct?

Senior
  1. A.Core test acceptance — sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade
  2. B.Core test acceptance — concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent
  3. C.Core test acceptance — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  4. D.Core test acceptance — IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads
Reveal the answer + AI explanation — free account

19. What is Aggregate mechanical tests?

Mid
  1. A.IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads
  2. B.IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength
  3. C.IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  4. D.surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
Reveal the answer + AI explanation — free account

20. Which term means: "IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads"?

Mid
  1. A.Rebound hammer test
  2. B.Aggregate mechanical tests
  3. C.Slump test
  4. D.Core test acceptance
Reveal the answer + AI explanation — free account

21. Which statement is correct?

Mid
  1. A.Aggregate mechanical tests — activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
  2. B.Aggregate mechanical tests — IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads
  3. C.Aggregate mechanical tests — concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent
  4. D.Aggregate mechanical tests — IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³
Reveal the answer + AI explanation — free account

22. What is Field density test?

Mid
  1. A.surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  2. B.IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  3. C.formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  4. D.sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade
Reveal the answer + AI explanation — free account

23. Which term means: "sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade"?

Mid
  1. A.Field density test
  2. B.Sampling frequency
  3. C.Inspection and test plan
  4. D.Slump test
Reveal the answer + AI explanation — free account

24. Which statement is correct?

Mid
  1. A.Field density test — activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
  2. B.Field density test — sand replacement or core cutter per IS 2720 checks in-situ dry density, with MoRTH requiring 97 percent of Proctor for the top 500 mm of subgrade
  3. C.Field density test — IS 1199 cone 300 mm high filled in three layers of 25 tamps and lifted, with true slump measured and shear or collapse slumps rejected
  4. D.Field density test — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
Reveal the answer + AI explanation — free account

25. What is Inspection and test plan?

Mid
  1. A.IS 456 requires one sample for 1 to 5 m³, two for 6 to 15, three for 16 to 30, four for 31 to 50 and one more per additional 50 m³
  2. B.IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  3. C.surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  4. D.activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
Reveal the answer + AI explanation — free account

26. Which term means: "activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point"?

Mid
  1. A.Core test acceptance
  2. B.Cube compressive test
  3. C.Inspection and test plan
  4. D.Slump test
Reveal the answer + AI explanation — free account

27. Which statement is correct?

Mid
  1. A.Inspection and test plan — concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent
  2. B.Inspection and test plan — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
  3. C.Inspection and test plan — IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength
  4. D.Inspection and test plan — activity-wise matrix listing reference specification, test frequency, acceptance criteria, responsibility and whether the client holds, witnesses or reviews each point
Reveal the answer + AI explanation — free account

28. What is Non-conformance report?

Senior
  1. A.IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  2. B.IS 2386 Part 4 impact and crushing values are limited to 30 percent for wearing surfaces and 45 percent elsewhere, with combined flakiness and elongation under 35 percent for roads
  3. C.concrete is accepted when the average of cores is at least 85 percent of the cube strength and no individual core falls below 75 percent
  4. D.formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
Reveal the answer + AI explanation — free account

29. Which term means: "formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject"?

Senior
  1. A.Field density test
  2. B.Slump test
  3. C.Sampling frequency
  4. D.Non-conformance report
Reveal the answer + AI explanation — free account

30. Which statement is correct?

Senior
  1. A.Non-conformance report — IS 516 Part 5 grades concrete above 4.5 km/s as excellent, 3.5 to 4.5 good, 3.0 to 3.5 medium and below 3.0 doubtful, revealing honeycombs and cracks
  2. B.Non-conformance report — surface-hardness index converted to strength through a calibration curve with about 25 percent accuracy, useful for uniformity surveys not acceptance
  3. C.Non-conformance report — IS 516 tests three 150 mm cubes per sample at 28 days under 14 N/mm² per minute, the 7-day result reaching roughly two-thirds of the final strength
  4. D.Non-conformance report — formal record of work deviating from specification with root cause, corrective and preventive action and a disposition of accept-as-is, rework, repair or reject
Reveal the answer + AI explanation — free account

Free to start

Answers, AI explanations, and a free readiness check

Sign up free to check your answers with explanations, ask the AI tutor anything on any question, and take the free 2-minute readiness check for a scored result. The full AI mock interview, scored like a real panel, unlocks with Pro.

Practice QA/QC & Testing free