24,000+ questions & coding problemsSoftware & IT16,274 questionsGovernment jobs26 examsAptitudenew questions every timeAI practice interviewwith feedback65 topics to practiseMechanical1,149 questionsGATE ME9 papersEngineering Mathematics381 questions2-minute checkfreeDSA Problems1,422Civil1,005 questionsGATE CE9 papersCS Fundamentals1,209 questionsYour scores6 skillsSystem Design25Electrical / EEE1,047 questionsGATE EE9 papersRun your codeC++ · Java · PythonLow-Level Design144Electronics & Comm.975 questionsGATE EC9 papersAI help on every questionFull-Stack6,282Chemical1,005 questionsGATE CH9 papersAI whiteboardsystem designWork abroadEurope · remote · transfersESE ME1 paperGATE practice papers2019–2026ESE CE1 paperDate alertsbefore the last dateESE EE1 paperBehavioural courseHR round practiceESE ET1 paperResume optimizerSSC JE ME1 paperApplication trackerSSC JE CE1 paperCompany-wise prepSSC JE EE1 paperRole roadmapsRRB JE1 subjectPriced in ₹UPI · cardsISRO SC1 paperGATE CS9 papersIBPS SO IT1 paperUGC NET CS1 paperSSC CGL26 papersIBPS PO26 papersRRB NTPC26 papersSSC CHSL26 papersIBPS Clerk26 papersSBI Clerk26 papersRRB Group D26 papersSSC CPO26 papersSSC GD26 papers

Contracts & Claims interview questions

27 real Contracts & Claims questions from the Site & Project Mgmt bank, as asked in Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd — free to start.

1. What is Item-rate vs lump-sum vs EPC?

Junior
  1. A.NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  2. B.12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
  3. C.payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
  4. D.Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
Reveal the answer + AI explanation — free account

2. Which term means: "payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements"?

Junior
  1. A.Item-rate vs lump-sum vs EPC
  2. B.Hybrid annuity model
  3. C.FIDIC books
  4. D.Defect liability period
Reveal the answer + AI explanation — free account

3. Which statement is correct?

Junior
  1. A.Item-rate vs lump-sum vs EPC — pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  2. B.Item-rate vs lump-sum vs EPC — NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  3. C.Item-rate vs lump-sum vs EPC — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  4. D.Item-rate vs lump-sum vs EPC — payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
Reveal the answer + AI explanation — free account

4. What is Hybrid annuity model?

Junior
  1. A.Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
  2. B.NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  3. C.payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
  4. D.instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
Reveal the answer + AI explanation — free account

5. Which term means: "NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority"?

Junior
  1. A.Retention money
  2. B.Hybrid annuity model
  3. C.Dispute resolution ladder
  4. D.FIDIC books
Reveal the answer + AI explanation — free account

6. Which statement is correct?

Junior
  1. A.Hybrid annuity model — NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  2. B.Hybrid annuity model — payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
  3. C.Hybrid annuity model — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  4. D.Hybrid annuity model — 12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
Reveal the answer + AI explanation — free account

7. What is Retention money?

Junior
  1. A.pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  2. B.5 to 10 percent held back from each running bill as security, released partly at completion and the rest after the defect liability period or replaced by bank guarantee
  3. C.Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
  4. D.12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
Reveal the answer + AI explanation — free account

8. Which term means: "5 to 10 percent held back from each running bill as security, released partly at completion and the rest after the defect liability period or replaced by bank guarantee"?

Junior
  1. A.Dispute resolution ladder
  2. B.Hybrid annuity model
  3. C.Extension of time
  4. D.Retention money
Reveal the answer + AI explanation — free account

9. Which statement is correct?

Junior
  1. A.Retention money — NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  2. B.Retention money — instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  3. C.Retention money — 5 to 10 percent held back from each running bill as security, released partly at completion and the rest after the defect liability period or replaced by bank guarantee
  4. D.Retention money — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
Reveal the answer + AI explanation — free account

10. What is FIDIC books?

Mid
  1. A.instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  2. B.Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
  3. C.NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  4. D.12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
Reveal the answer + AI explanation — free account

11. Which term means: "Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices"?

Mid
  1. A.Item-rate vs lump-sum vs EPC
  2. B.FIDIC books
  3. C.Defect liability period
  4. D.Variation
Reveal the answer + AI explanation — free account

12. Which statement is correct?

Mid
  1. A.FIDIC books — Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
  2. B.FIDIC books — Engineer's decision, then dispute board or conciliation, then arbitration under the Arbitration and Conciliation Act 1996 with awards due within 12 months of pleadings
  3. C.FIDIC books — payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
  4. D.FIDIC books — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
Reveal the answer + AI explanation — free account

13. What is Variation?

Mid
  1. A.12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
  2. B.pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  3. C.Engineer's decision, then dispute board or conciliation, then arbitration under the Arbitration and Conciliation Act 1996 with awards due within 12 months of pleadings
  4. D.instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
Reveal the answer + AI explanation — free account

14. Which term means: "instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it"?

Mid
  1. A.Retention money
  2. B.Variation
  3. C.Defect liability period
  4. D.Hybrid annuity model
Reveal the answer + AI explanation — free account

15. Which statement is correct?

Mid
  1. A.Variation — instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  2. B.Variation — Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
  3. C.Variation — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  4. D.Variation — 12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
Reveal the answer + AI explanation — free account

16. What is Extension of time?

Mid
  1. A.5 to 10 percent held back from each running bill as security, released partly at completion and the rest after the defect liability period or replaced by bank guarantee
  2. B.pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  3. C.grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  4. D.Engineer's decision, then dispute board or conciliation, then arbitration under the Arbitration and Conciliation Act 1996 with awards due within 12 months of pleadings
Reveal the answer + AI explanation — free account

17. Which term means: "grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost"?

Mid
  1. A.Dispute resolution ladder
  2. B.Extension of time
  3. C.Liquidated damages
  4. D.Defect liability period
Reveal the answer + AI explanation — free account

18. Which statement is correct?

Mid
  1. A.Extension of time — payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
  2. B.Extension of time — 12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
  3. C.Extension of time — instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  4. D.Extension of time — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
Reveal the answer + AI explanation — free account

19. What is Liquidated damages?

Senior
  1. A.NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  2. B.Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
  3. C.instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  4. D.pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
Reveal the answer + AI explanation — free account

20. Which term means: "pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate"?

Senior
  1. A.Dispute resolution ladder
  2. B.Defect liability period
  3. C.Liquidated damages
  4. D.FIDIC books
Reveal the answer + AI explanation — free account

21. Which statement is correct?

Senior
  1. A.Liquidated damages — payment on measured quantities at quoted BOQ rates, a fixed price for a defined scope, or single-point design-build responsibility against employer's requirements
  2. B.Liquidated damages — pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  3. C.Liquidated damages — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  4. D.Liquidated damages — 5 to 10 percent held back from each running bill as security, released partly at completion and the rest after the defect liability period or replaced by bank guarantee
Reveal the answer + AI explanation — free account

22. What is Defect liability period?

Mid
  1. A.instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  2. B.grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  3. C.12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
  4. D.Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
Reveal the answer + AI explanation — free account

23. Which term means: "12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released"?

Mid
  1. A.FIDIC books
  2. B.Dispute resolution ladder
  3. C.Variation
  4. D.Defect liability period
Reveal the answer + AI explanation — free account

24. Which statement is correct?

Mid
  1. A.Defect liability period — NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  2. B.Defect liability period — 12 months after completion during which the contractor rectifies defects at own cost, after which the security deposit is released
  3. C.Defect liability period — pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  4. D.Defect liability period — Red for employer-designed measured works, Yellow for plant and design-build, Silver for EPC turnkey, with 2017 editions and 28-day claim notices
Reveal the answer + AI explanation — free account

25. What is Dispute resolution ladder?

Senior
  1. A.NHAI pays 40 percent of project cost during construction and the balance as annuities with interest over 15 years of operation, keeping toll risk with the authority
  2. B.instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
  3. C.Engineer's decision, then dispute board or conciliation, then arbitration under the Arbitration and Conciliation Act 1996 with awards due within 12 months of pleadings
  4. D.grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
Reveal the answer + AI explanation — free account

26. Which term means: "Engineer's decision, then dispute board or conciliation, then arbitration under the Arbitration and Conciliation Act 1996 with awards due within 12 months of pleadings"?

Senior
  1. A.Liquidated damages
  2. B.Hybrid annuity model
  3. C.Dispute resolution ladder
  4. D.Retention money
Reveal the answer + AI explanation — free account

27. Which statement is correct?

Senior
  1. A.Dispute resolution ladder — pre-agreed compensation for delay, typically 1.5 percent of contract value per month capped at 10 percent under CPWD GCC, enforceable only as a genuine pre-estimate
  2. B.Dispute resolution ladder — grant of extra contract duration for employer-caused or excusable delay, preserving liquidated damages and given with or without prolongation cost
  3. C.Dispute resolution ladder — Engineer's decision, then dispute board or conciliation, then arbitration under the Arbitration and Conciliation Act 1996 with awards due within 12 months of pleadings
  4. D.Dispute resolution ladder — instructed change in scope, quantity or quality priced at contract rates within the deviation limit and at derived or market rates beyond it
Reveal the answer + AI explanation — free account

Free to start

Answers, AI explanations, and a free readiness check

Sign up free to check your answers with explanations, ask the AI tutor anything on any question, and take the free 2-minute readiness check for a scored result. The full AI mock interview, scored like a real panel, unlocks with Pro.

Practice Contracts & Claims free