24,000+ questions & coding problemsSoftware & IT16,274 questionsGovernment jobs26 examsAptitudenew questions every timeAI practice interviewwith feedback65 topics to practiseMechanical1,149 questionsGATE ME9 papersEngineering Mathematics381 questions2-minute checkfreeDSA Problems1,422Civil1,005 questionsGATE CE9 papersCS Fundamentals1,209 questionsYour scores6 skillsSystem Design25Electrical / EEE1,047 questionsGATE EE9 papersRun your codeC++ · Java · PythonLow-Level Design144Electronics & Comm.975 questionsGATE EC9 papersAI help on every questionFull-Stack6,282Chemical1,005 questionsGATE CH9 papersAI whiteboardsystem designWork abroadEurope · remote · transfersESE ME1 paperGATE practice papers2019–2026ESE CE1 paperDate alertsbefore the last dateESE EE1 paperBehavioural courseHR round practiceESE ET1 paperResume optimizerSSC JE ME1 paperApplication trackerSSC JE CE1 paperCompany-wise prepSSC JE EE1 paperRole roadmapsRRB JE1 subjectPriced in ₹UPI · cardsISRO SC1 paperGATE CS9 papersIBPS SO IT1 paperUGC NET CS1 paperSSC CGL26 papersIBPS PO26 papersRRB NTPC26 papersSSC CHSL26 papersIBPS Clerk26 papersSBI Clerk26 papersRRB Group D26 papersSSC CPO26 papersSSC GD26 papers

Project Planning & Scheduling interview questions

27 real Project Planning & Scheduling questions from the Site & Project Mgmt bank, as asked in Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd — free to start.

1. What is CPM vs PERT?

Junior
  1. A.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
  2. B.shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
  3. C.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  4. D.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
Reveal the answer + AI explanation — free account

2. Which term means: "deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates"?

Junior
  1. A.CPM vs PERT
  2. B.Resource levelling vs smoothing
  3. C.Crashing
  4. D.Primavera P6
Reveal the answer + AI explanation — free account

3. Which statement is correct?

Junior
  1. A.CPM vs PERT — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  2. B.CPM vs PERT — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  3. C.CPM vs PERT — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  4. D.CPM vs PERT — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
Reveal the answer + AI explanation — free account

4. What is Critical path?

Junior
  1. A.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  2. B.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  3. C.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  4. D.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
Reveal the answer + AI explanation — free account

5. Which term means: "longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion"?

Junior
  1. A.Resource levelling vs smoothing
  2. B.Look-ahead schedule
  3. C.S-curve
  4. D.Critical path
Reveal the answer + AI explanation — free account

6. Which statement is correct?

Junior
  1. A.Critical path — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  2. B.Critical path — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  3. C.Critical path — enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
  4. D.Critical path — longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
Reveal the answer + AI explanation — free account

7. What is Total float vs free float?

Junior
  1. A.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
  2. B.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  3. C.shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
  4. D.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
Reveal the answer + AI explanation — free account

8. Which term means: "time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former"?

Junior
  1. A.Total float vs free float
  2. B.CPM vs PERT
  3. C.Primavera P6
  4. D.Crashing
Reveal the answer + AI explanation — free account

9. Which statement is correct?

Junior
  1. A.Total float vs free float — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  2. B.Total float vs free float — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
  3. C.Total float vs free float — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  4. D.Total float vs free float — shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
Reveal the answer + AI explanation — free account

10. What is Primavera P6?

Mid
  1. A.enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
  2. B.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  3. C.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  4. D.shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
Reveal the answer + AI explanation — free account

11. Which term means: "enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date"?

Mid
  1. A.Crashing
  2. B.Look-ahead schedule
  3. C.Earned value metrics
  4. D.Primavera P6
Reveal the answer + AI explanation — free account

12. Which statement is correct?

Mid
  1. A.Primavera P6 — longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
  2. B.Primavera P6 — shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
  3. C.Primavera P6 — enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
  4. D.Primavera P6 — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Reveal the answer + AI explanation — free account

13. What is S-curve?

Junior
  1. A.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  2. B.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  3. C.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  4. D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Reveal the answer + AI explanation — free account

14. Which term means: "plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow"?

Junior
  1. A.Primavera P6
  2. B.S-curve
  3. C.Resource levelling vs smoothing
  4. D.CPM vs PERT
Reveal the answer + AI explanation — free account

15. Which statement is correct?

Junior
  1. A.S-curve — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  2. B.S-curve — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  3. C.S-curve — shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
  4. D.S-curve — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
Reveal the answer + AI explanation — free account

16. What is Earned value metrics?

Mid
  1. A.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
  2. B.shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
  3. C.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  4. D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Reveal the answer + AI explanation — free account

17. Which term means: "CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI"?

Mid
  1. A.Earned value metrics
  2. B.Primavera P6
  3. C.Total float vs free float
  4. D.Resource levelling vs smoothing
Reveal the answer + AI explanation — free account

18. Which statement is correct?

Mid
  1. A.Earned value metrics — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  2. B.Earned value metrics — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  3. C.Earned value metrics — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  4. D.Earned value metrics — longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
Reveal the answer + AI explanation — free account

19. What is Look-ahead schedule?

Mid
  1. A.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  2. B.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  3. C.enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
  4. D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Reveal the answer + AI explanation — free account

20. Which term means: "rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete"?

Mid
  1. A.Resource levelling vs smoothing
  2. B.Crashing
  3. C.Total float vs free float
  4. D.Look-ahead schedule
Reveal the answer + AI explanation — free account

21. Which statement is correct?

Mid
  1. A.Look-ahead schedule — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
  2. B.Look-ahead schedule — shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
  3. C.Look-ahead schedule — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
  4. D.Look-ahead schedule — enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
Reveal the answer + AI explanation — free account

22. What is Resource levelling vs smoothing?

Senior
  1. A.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
  2. B.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
  3. C.shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
  4. D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Reveal the answer + AI explanation — free account

23. Which term means: "shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks"?

Senior
  1. A.Total float vs free float
  2. B.Resource levelling vs smoothing
  3. C.Primavera P6
  4. D.S-curve
Reveal the answer + AI explanation — free account

24. Which statement is correct?

Senior
  1. A.Resource levelling vs smoothing — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  2. B.Resource levelling vs smoothing — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
  3. C.Resource levelling vs smoothing — shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
  4. D.Resource levelling vs smoothing — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
Reveal the answer + AI explanation — free account

25. What is Crashing?

Senior
  1. A.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
  2. B.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
  3. C.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  4. D.shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
Reveal the answer + AI explanation — free account

26. Which term means: "shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change"?

Senior
  1. A.Crashing
  2. B.S-curve
  3. C.Earned value metrics
  4. D.Look-ahead schedule
Reveal the answer + AI explanation — free account

27. Which statement is correct?

Senior
  1. A.Crashing — shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
  2. B.Crashing — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
  3. C.Crashing — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
  4. D.Crashing — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
Reveal the answer + AI explanation — free account

Free to start

Answers, AI explanations, and a free readiness check

Sign up free to check your answers with explanations, ask the AI tutor anything on any question, and take the free 2-minute readiness check for a scored result. The full AI mock interview, scored like a real panel, unlocks with Pro.