24,000+ questions & coding problemsSoftware & IT16,274 questionsGovernment jobs26 examsAptitudenew questions every timeAI practice interviewwith feedback65 topics to practiseMechanical1,149 questionsGATE ME9 papersEngineering Mathematics381 questions2-minute checkfreeDSA Problems1,422Civil1,005 questionsGATE CE9 papersCS Fundamentals1,209 questionsYour scores6 skillsSystem Design25Electrical / EEE1,047 questionsGATE EE9 papersRun your codeC++ · Java · PythonLow-Level Design144Electronics & Comm.975 questionsGATE EC9 papersAI help on every questionFull-Stack6,282Chemical1,005 questionsGATE CH9 papersAI whiteboardsystem designWork abroadEurope · remote · transfersESE ME1 paperGATE practice papers2019–2026ESE CE1 paperDate alertsbefore the last dateESE EE1 paperBehavioural courseHR round practiceESE ET1 paperResume optimizerSSC JE ME1 paperApplication trackerSSC JE CE1 paperCompany-wise prepSSC JE EE1 paperRole roadmapsRRB JE1 subjectPriced in ₹UPI · cardsISRO SC1 paperGATE CS9 papersIBPS SO IT1 paperUGC NET CS1 paperSSC CGL26 papersIBPS PO26 papersRRB NTPC26 papersSSC CHSL26 papersIBPS Clerk26 papersSBI Clerk26 papersRRB Group D26 papersSSC CPO26 papersSSC GD26 papers

Production Planning & Control interview questions

27 real Production Planning & Control questions from the Production & Plant bank, as asked in Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd — free to start.

1. What is Takt time?

Junior
  1. A.available production time divided by customer demand, the pace at which one unit must leave the line
  2. B.sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
  3. C.actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  4. D.computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time
Reveal the answer + AI explanation — free account

3. Which statement is correct?

Junior
  1. A.Takt time — availability × performance × quality of a machine, with 85% regarded as world class
  2. B.Takt time — actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  3. C.Takt time — sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
  4. D.Takt time — available production time divided by customer demand, the pace at which one unit must leave the line
Reveal the answer + AI explanation — free account

4. What is Cycle time?

Junior
  1. A.resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  2. B.availability × performance × quality of a machine, with 85% regarded as world class
  3. C.actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  4. D.computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time
Reveal the answer + AI explanation — free account

6. Which statement is correct?

Junior
  1. A.Cycle time — availability × performance × quality of a machine, with 85% regarded as world class
  2. B.Cycle time — computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time
  3. C.Cycle time — actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  4. D.Cycle time — breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down
Reveal the answer + AI explanation — free account

7. What is Manufacturing lead time?

Junior
  1. A.available production time divided by customer demand, the pace at which one unit must leave the line
  2. B.resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  3. C.theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  4. D.elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
Reveal the answer + AI explanation — free account

8. Which term means: "elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest"?

Junior
  1. A.Six big losses
  2. B.Takt time
  3. C.Bottleneck
  4. D.Manufacturing lead time
Reveal the answer + AI explanation — free account

9. Which statement is correct?

Junior
  1. A.Manufacturing lead time — resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  2. B.Manufacturing lead time — elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
  3. C.Manufacturing lead time — actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  4. D.Manufacturing lead time — available production time divided by customer demand, the pace at which one unit must leave the line
Reveal the answer + AI explanation — free account

10. What is Material requirements planning?

Mid
  1. A.computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time
  2. B.available production time divided by customer demand, the pace at which one unit must leave the line
  3. C.theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  4. D.resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
Reveal the answer + AI explanation — free account

11. Which term means: "computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time"?

Mid
  1. A.Six big losses
  2. B.Material requirements planning
  3. C.Cycle time
  4. D.Bottleneck
Reveal the answer + AI explanation — free account

12. Which statement is correct?

Mid
  1. A.Material requirements planning — actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  2. B.Material requirements planning — computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time
  3. C.Material requirements planning — availability × performance × quality of a machine, with 85% regarded as world class
  4. D.Material requirements planning — elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
Reveal the answer + AI explanation — free account

13. What is OEE?

Mid
  1. A.available production time divided by customer demand, the pace at which one unit must leave the line
  2. B.elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
  3. C.resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  4. D.availability × performance × quality of a machine, with 85% regarded as world class
Reveal the answer + AI explanation — free account

15. Which statement is correct?

Mid
  1. A.OEE — theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  2. B.OEE — sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
  3. C.OEE — availability × performance × quality of a machine, with 85% regarded as world class
  4. D.OEE — resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
Reveal the answer + AI explanation — free account

16. What is Six big losses?

Mid
  1. A.elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
  2. B.theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  3. C.sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
  4. D.breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down
Reveal the answer + AI explanation — free account

17. Which term means: "breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down"?

Mid
  1. A.Six big losses
  2. B.Drum-buffer-rope
  3. C.Cycle time
  4. D.Material requirements planning
Reveal the answer + AI explanation — free account

18. Which statement is correct?

Mid
  1. A.Six big losses — elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
  2. B.Six big losses — sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
  3. C.Six big losses — actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  4. D.Six big losses — breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down
Reveal the answer + AI explanation — free account

19. What is Line balance efficiency?

Mid
  1. A.availability × performance × quality of a machine, with 85% regarded as world class
  2. B.available production time divided by customer demand, the pace at which one unit must leave the line
  3. C.resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  4. D.sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
Reveal the answer + AI explanation — free account

20. Which term means: "sum of task times divided by the number of stations times the cycle time, with balance delay as its complement"?

Mid
  1. A.Material requirements planning
  2. B.Manufacturing lead time
  3. C.Line balance efficiency
  4. D.OEE
Reveal the answer + AI explanation — free account

21. Which statement is correct?

Mid
  1. A.Line balance efficiency — sum of task times divided by the number of stations times the cycle time, with balance delay as its complement
  2. B.Line balance efficiency — elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
  3. C.Line balance efficiency — theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  4. D.Line balance efficiency — available production time divided by customer demand, the pace at which one unit must leave the line
Reveal the answer + AI explanation — free account

22. What is Bottleneck?

Senior
  1. A.computing dependent-demand component needs by exploding the BOM against the master schedule, netting inventory and offsetting by lead time
  2. B.actual time a workstation takes to complete one unit, which must be at or below the takt time for the line to keep up
  3. C.available production time divided by customer demand, the pace at which one unit must leave the line
  4. D.resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
Reveal the answer + AI explanation — free account

24. Which statement is correct?

Senior
  1. A.Bottleneck — availability × performance × quality of a machine, with 85% regarded as world class
  2. B.Bottleneck — available production time divided by customer demand, the pace at which one unit must leave the line
  3. C.Bottleneck — resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  4. D.Bottleneck — breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down
Reveal the answer + AI explanation — free account

25. What is Drum-buffer-rope?

Senior
  1. A.elapsed time from order release to completion, made up of queue, setup, run and move time with queue usually the largest
  2. B.available production time divided by customer demand, the pace at which one unit must leave the line
  3. C.theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  4. D.breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down
Reveal the answer + AI explanation — free account

26. Which term means: "theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption"?

Senior
  1. A.Bottleneck
  2. B.Takt time
  3. C.Drum-buffer-rope
  4. D.Cycle time
Reveal the answer + AI explanation — free account

27. Which statement is correct?

Senior
  1. A.Drum-buffer-rope — resource whose capacity is below the demand placed on it, so an hour lost there is an hour lost for the whole plant
  2. B.Drum-buffer-rope — breakdowns, setup and adjustment, minor stops, reduced speed, start-up rejects and production rejects, the categories that pull OEE down
  3. C.Drum-buffer-rope — theory-of-constraints scheduling where the constraint sets the pace, a time buffer protects it and material release is tied to its consumption
  4. D.Drum-buffer-rope — availability × performance × quality of a machine, with 85% regarded as world class
Reveal the answer + AI explanation — free account

Free to start

Answers, AI explanations, and a free readiness check

Sign up free to check your answers with explanations, ask the AI tutor anything on any question, and take the free 2-minute readiness check for a scored result. The full AI mock interview, scored like a real panel, unlocks with Pro.

Practice Production Planning & Control free